Managing infrastructure projects on nuclear-regulated sites
On January 10,2020 the National Audit Office (NAO) reports that the Ministry of Defence’s (MoD) poor management of three critical infrastructure projects on its nuclear-regulated sites has contributed to a combined cost increase of £1.35 billion and delays of between 1.7 and 6.3 years. After problems in the early stages of the projects, the MoD has made progress, with some of the construction now complete. However, it still needs to manage the remaining commercial risks and learn the lessons for future projects.
The UK’s continuous-at-sea nuclear deterrent relies on a network of equipment, people and infrastructure, often referred to as the Defence Nuclear Enterprise.1 To maintain this network, the MOD needs to complete three complex construction projects, valued at £2.5 billion together.
The three projects are:
. MENSA: a new nuclear warhead assembly and disassembly
facility, valued at £1.8 billion, at the Atomic Weapons
Establishment (AWE)-operated site in Burghfield (Reading).
. Core production capability (CPC) facilities: upgraded
facilities, costing at least £474 million, at the Rolls
Royce-operated site in Raynesway (Derby) to produce the
latest nuclear reactor core designs.
. Primary build facility: new facilities at the BAE Systems-
operated dockyard in Barrow-in-Furness (Cumbria), costing
£240 million to upgrade aging facilities and support
improved submarine construction techniques.
Along with the risks inherent in all major infrastructure projects, there are unique challenges with these projects. They include the need to comply with additional nuclear-related regulations, the limited pool of suppliers and the complexity of the designs. Problems in the earlier and riskier stages of these projects have caused delays and cost increases.
Some of the designs may have been more costly than necessary, mainly as a result of construction starting before the requirements or designs were fully developed, and changes to the project management or commercial approach. The way that the MoD set up the contracts also means that it, and not its contractors, must foot the bill for these cost increases as it did not share out the financial risks.
The delays to the projects have broader implications for nuclear work, which the MoD must manage. For example, following delays to MENSA, the MoD and AWE had to continue using existing infrastructure. The MoD expects it will have spent £21 million between 2016-17 and 2019-20 on site upgrades to continue to comply with regulations and be able to use the Burghfield site.
The MoD could have learnt more from the early stages of other nuclear infrastructure projects concluded in the UK and elsewhere. Similar challenges arose for the MoD in the 1980s and 1990s, as well as in American defence projects and UK civil nuclear projects, such as at Sellafield.
All the projects have now progressed and most of the facilities are taking shape. The MENSA facility was completed in October 2019, subject to fit out, and the first of the CPC facilities is expected to be completed in early 2020. Construction of one of the Primary build facility buildings is also largely complete. The MoD has made changes to improve its oversight of infrastructure projects and its relationships with contractors and regulators. Some contracts have also been renegotiated or improved for later phases with the aim of reducing costs going forward.
source: UK National Audit Office
- 301 reads
Human Rights
Ringing FOWPAL’s Peace Bell for the World:Nobel Peace Prize Laureates’ Visions and Actions
Protecting the World’s Cultural Diversity for a Sustainable Future
The Peace Bell Resonates at the 27th Eurasian Economic Summit
Declaration of World Day of the Power of Hope Endorsed by People in 158 Nations
Puppet Show I International Friendship Day 2020