IAEA Concludes Safety Review at Dukovany Nuclear Power Plant in Czech Republic
An international team of nuclear safety experts led by the International Atomic Energy Agency (IAEA) completed an assessment of long-term operational safety at the Dukovany Nuclear Power Plant in the Czech Republic.
The Safety Aspects of Long Term Operation (SALTO) review team was assembled at the request of the Czech Nuclear Power Company (CEZ). The in-depth review, which began on 18 November, focused on aspects essential to the safe long-term operation of the plant’s four reactors.
The SALTO team reviewed the plant’s organization and programmes related to its long term operation, including human resources and knowledge management. The conclusions of SALTO reviews are based on the IAEA Safety Standards.
The team identified a number of good practices and good performances at the plant that will be shared with the nuclear industry globally including:
•A comprehensive Reactor Pressure Vessel surveillance programme;
•Active and passive radiation dosimeters installed by the plant in many locations in the containment area; and
•An effective maintenance strategy based on an engineering process focusing on the reliability of the technical system, implemented by the plant.
The team identified several areas where it made proposals for improvements to operational safety including:
•Rather than limiting the plant’s approach for the long-term operation to the 10-year licensing period, it should focus on the full time span;
•Management review and management programmes for ageing civil structures need to be completed; and
•Coordination between key functions and partners for the long-term operation must ensure that relevant documents, data and knowledge are being systematically reviewed, archived and shared.
The Dukovany plant management are committed to implementing the recommendations and requested that the IAEA schedule a follow-up mission in approximately 18 months.
The team handed a draft review report to the plant management. This draft report, including any comments from the plant and the Czech Nuclear Regulatory Authority (SUJB), will be reviewed at IAEA headquarters. A final report will be submitted to the plant, to the SUJB and the Czech government within three months.
The review team comprised experts from Canada, Finland, Hungary, Sweden, the Netherlands, and the IAEA.
Source: International Atomic Energy Agency
- 270 reads
Human Rights
Conscience, Hope, and Action: Keys to Global Peace and Sustainability
Ringing FOWPAL’s Peace Bell for the World:Nobel Peace Prize Laureates’ Visions and Actions
Protecting the World’s Cultural Diversity for a Sustainable Future
The Peace Bell Resonates at the 27th Eurasian Economic Summit
Puppet Show I International Friendship Day 2020